The last public-access point anyone published for the Avila Pier was Bent 50. In February 2026, KSBY reported that walkers could go only that far, "a little less than half of the pier." Under the deck, the work is already further along. The Port San Luis Harbor District's staff report for its October 27 board meeting says full restoration through Bent 60 is complete. The contractor, Power Engineering, is scheduled to stay onsite through December, with repairs expected to reach Bents 70 to 74.
Two things limit how fast the next section comes along: money the District has not found yet, and a construction season that ends every winter. The rebuilt deck past Bent 50 shows what is possible. The $700,000 still missing on the way to Bent 80, and the end-of-December demobilization date, show how fast the rest of it can happen.
Eleven Years, Counted in Bents
A bent is one of the cross-frames of pilings and caps that hold up the deck. Harbor District documents track progress by bent number, counting out from the shore. The pier's history since its closure reads most clearly as a series of moving targets:
- June 2015. The pier closed to the public after an engineering inspection raised safety concerns, KCBX reported at the time.
- 2017 to 2019. According to Friends of Avila Pier, engineering surveys found that restoring the pier was feasible, so it did not need full replacement.
- January 2023. Storms separated 139 stringers, mostly between Bents 89 and 109, according to the District's emergency repair request for proposals.
- June 2024. KSBY reported that a partial reopening was expected by the end of 2024.
- August 2025. Walkers could reach about Bent 50, and Friends of Avila Pier hoped to extend access to Bent 70, per KSBY.
- February 2026. Harbor District facilities manager Dustin Barth told KSBY that construction up to Bent 80 would start in the spring.
- April 20, 2026. The board adopted Resolution No. 2026-05, which declared an emergency and allowed the repair work to proceed without competitive bidding.
- October 2026. Restoration through Bent 60 is complete, with work continuing toward Bents 70 to 74 through December.
Each milestone has moved further out over time, and none of them came with a public reopening date. The October report doesn't give one either. A restored bent is a construction milestone. Whether it opens to walkers is up to the District.
Why the Work Stops in Winter
State law makes the emergency declaration temporary by design. Under Public Contract Code section 22050, the board has to review the work at every regular meeting until the project is finished. That is why the same Avila Pier resolution comes up on agenda after agenda. The October staff report gives the reason for continuing: "Avila Pier continues to exhibit significant deterioration, which will progressively worsen until repairs are executed."
Ron Pigeon, secretary and treasurer of Friends of Avila Pier, explained to KSBY in an August 2026 interview why skipping the bidding process matters:
"That can speed up for critical months because there's only so many months during the year that they can actually do construction. During the winter months, they can't do much. Partly because of the weather and partly because of restrictions imposed by the Coastal Commission."
The 2021 Coastal Commission staff report for the pier's rehabilitation permit lays out what that means in practice. The proposed conditions bar mechanical pile driving within 50 feet of identified contamination from January 1 through April 30. If pile driving is proposed between January 1 and May 31, the steelhead migration season, the District has to consult wildlife agencies every month, and pile driving stops in any month when either agency indicates fish are migrating. From February 15 through September 1, bird surveys come before construction, and work near an active nest has to stop until the nest is no longer in use.
These are targeted conditions. They do not ban all winter work. Together with winter swells, though, they cover most of the first half of the year. The District has scheduled demobilization for the end of December, and continuing repairs through December depends on the weather. Crews have roughly the next eight weeks to get as far as they can.
The Money Between Bent 60 and Bent 80
Most of the material needed for repairs through Bent 80 is already onsite, according to the October report. The budget is what falls short:
| Item | Figure | Status in the October 27 staff report |
|---|---|---|
| FY 2026–27 Avila Pier Rehabilitation budget | $1,328,000 | Staff expects emergency work to stay within it |
| Initial construction proposals | More than $1 million over budget | Value engineering and scope changes underway |
| Gap to reach the Bent 80 milestone | About $700,000 | District exploring financing strategies |
| FEMA project 715265 | $228,163.62 | Funds obligated |
| FEMA project 716313 | $862,767.67 | Initial application declined, appeal pending |
The appealed FEMA request is larger than the gap. If the appeal succeeds, it could cover the shortfall to Bent 80. If it fails, the District has to find the money somewhere else. The District already has a cost-cutting plan. Its own staff will install the longitudinal bracing, decking and hardware, which saves contractor time.
The October report is a staff recommendation prepared for the board. The figures above reflect the District's position going into that meeting.
The outer section matters for more than walking. A January 2026 feasibility memo, prepared for the District by the engineering firm Moffatt & Nichol, identified Bent 74 as a workable location for a relocated boat landing, replacing the existing landing near Bent 95. That design is still a concept. It also falls inside the stretch the current work is trying to reach.
Who Has Been Paying Into It
Much of the money for the pier has come from the community. Friends of Avila Pier is a 501(c)(3) formed to raise repair and maintenance funds. In June 2024, KSBY reported that the group had granted $345,000 to the Harbor District since 2019, including a $100,000 donation that week. As of August 2025, Pigeon told KSBY the group had raised $600,000 toward a $1 million goal since 2019, more than $40,000 of it after Memorial Day 2025.
That 2025 total is the most recent one on record. The $1 million goal still appears on the group's donation page, which accepts online gifts by card or bank debit, plus checks by mail.
The donor plaques on the restored railing come from the plaque program. Cumulative gifts of $1,000 to $4,999 and $5,000 to $14,999 earn railing plaques. Gifts of $15,000 or more earn a larger plaque, subject to how many light posts are available. Pigeon told KSBY the plaques help visitors see what the fundraising has paid for. The San Luis Yacht Club has also asked its members to raise $15,000 for the group.
When Pigeon spoke to KSBY in August, he said he was asking the public for donations to help close the gap to Bent 80. Compared with what the group has already raised, $700,000 is a large amount. The group reported raising $600,000 over about six years.
The Rest of the Waterfront Through Year-End
The work at Harford Pier this season is also about next year. The Harbor District is taking proposals for up to two 2027 charter-vessel licenses operating from Harford Pier. Eligible uses include whale watching, harbor cruises, wildlife tours, sailing excursions and fishing charters. Proposals and a $286 fee are due November 6 at 4:30 p.m. Pacific. Proposals are not the same as selected operators. Who runs trips from Harford in 2027 depends on what the District awards.
On Front Street, Santa's Doggie Parade steps off at 11 a.m. on November 28 at 404 Front St. Check-in runs from 10:30 to 10:45 a.m. outside the Custom House, and organizers ask for a $5 donation. When crews demobilize at the end of December, the restored deck will reach further than it did in February. How much of it is open to walkers will be up to the Harbor District.